Installation sequence and precautions of vertical multi-stage centrifugal pump

20 Apr 2021Email

A. Preparation before installation of vertical multi-stage centrifugal pump
   1. Prepare installation tools and lifting equipment;
  2. Check whether the parts of the multi-stage centrifugal pump unit are loose or damaged during transportation;
Vertical multi-stage centrifugal pump
   3. Check whether the foundation is level.

B. Installation sequence of vertical multi-stage centrifugal pump
   1. When the unit is transported to the site, the person with the base has already calibrated the pump and motor. When leveling the base, it is not necessary to remove the pump and motor, so the installation is very convenient
  2. Put the base on the foundation and put a wedge-shaped iron near the anchor bolts. The height of the base is 20-40 mm for filling with cement slurry after leveling;
  3. Check the levelness of the base with a spirit level, fill the base with cement slurry after leveling, and check the level again after the cement dries;
  4. When the power of the unit is large, the pump, motor and base may be packaged separately in order to facilitate transportation. At this time, users need to install and calibrate the pump unit by themselves. The method is as follows:
  A. Remove the dirt on the support plane of the base, the feet of the water pump and the feet of the motor, and place the pump and the motor on the base;
  B. Adjust the level of the pump shaft, and fix the pump on the base with bolts after leveling to prevent it from moving;
  C. Lift the motor, make the pump coupling and the motor coupling match, and lower the motor to the corresponding position on the base;
d. Adjust the gap between the two couplings to about 5mm, and correct whether the axis of the motor shaft and the pump shaft coincide. The method is to put a flat ruler on the coupling, and the outer circle of the two couplings should be in line with the flat ruler. If they are not coincident, the relative position of the motor or pump should be adjusted, or the pad should be adjusted with a thin iron sheet;
e. In order to check the installation accuracy, the gap between the two coupling planes should be measured with a feeler gauge at several different positions on the circumference of the coupling. The difference between the large and small gaps on the coupling plane should not exceed 0.3mm. The difference between the top and bottom or left and right of the end center line shall not exceed 0.1mm.
   5. When the unit does not have a base, it needs to be installed directly on the foundation. The method is similar to that of 4., but more attention should be paid to calibration.

C. Precautions for the installation of vertical multi-stage centrifugal pumps
   1. The pipeline should not be put on the pump during installation, otherwise the pump will be easily damaged;
  2. The anchor bolts must be tightened during installation, and the unit should be inspected every certain period of time to prevent it from loosening, so as to avoid severe vibration when the pump starts running and affect the performance of the pump
  3. Before installing the pump, carefully check whether there are hard objects (such as stones, iron sand, etc.) that affect the operation of the pump in the pump flow path to avoid damage to the flow components during the operation of the pump
4. For the convenience of maintenance and safe use, a regulating valve should be installed on the inlet and outlet pipes of the pump and a pressure gauge should be installed on the inlet and outlet flanges of the pump. For high-lift pumps, in order to prevent water hammer, Install a check valve in front of the outlet gate valve to deal with power loss accidents such as sudden power failure, so as to ensure that the pump runs under appropriate working conditions and prolong the service life of the pump;
  5. When the pump is used for suction lift occasions, it should be equipped with a bottom valve, and the inlet pipeline should not have too many bends, and there should be no water leakage or air leakage, so as not to affect the suction performance of the pump
   6. In order to prevent impurities from entering the pump. Blocking the flow passage and affecting performance, a filter should be installed in front of the pump inlet
  7. Rotate the rotor part of the water pump before installing the pipeline. There should be no friction or jamming. Otherwise, the pump should be disassembled to check the cause.

Related Pump Knowledge
More Pump Knowledge
02 May 2025
             With the rapid advancement of industrial development, multistage centrifugal pumps are increasingly wi...
Read more
25 Apr 2025
          There could be many reasons why a horizontal double-suction centrifugal pump fails to draw water. The following are...
Read more
17 Apr 2025
            In the modern industrial equipment system, multistage centrifugal pumps, as core fluid transfer devices, are...
Read more
09 Apr 2025
          In the mining industry, one of the pumps frequently used in mines is the slurry pump. This is a type of pump capabl...
Read more
Related Products
More
Split Case Pump
Split Case Pump
  • Capacity:60-33005m³/h
  • Head:0.95-30.2bar
  • Price:$2200-215000
Double Suction Pump
Double Suction Pump
  • Capacity:60-33005m³/h
  • Head:0.95-30.2bar
  • Price:$2200-215000
Single Stage Chemical Pump
Single Stage Chemical Pump
  • Capacity:5.5-2600m³/h
  • Head:1.6-25bar
  • Price:$4300-37000
End Suction Chemical Pump
End Suction Chemical Pump
  • Capacity:5.5~400m³/h
  • Head:0.42-12.5bar
  • Price:$560-9800
Need More Information?
Contact us for more details about our pump, solutions and services.
Contact ZB
Tel
0086 731 88192011
Email
Chat online
Leave a message
Name*
Tel
Email*
Area
Products
Split Case Pump
Metallurgy
Mining Industry
Urban Water Supply
Petrochemical
Light Industry
Electricity
Chemical Industry
Farmland Irrigation
Other
Provide your comments and questions.